Kabale Leaders Commission Shs285 Million Classroom Blocks Order Contractor To Fix Defects
The story
Kabale District leaders have commissioned two new twin classroom blocks at Butanda Secondary School, constructed at a cost of Shs285 million, while directing the contractor to complete all outstanding works before the defect's liability period expires.
The classroom blocks, located in Butanda Sub-county, are expected to improve the school's learning environment and ease pressure on existing infrastructure.
Details
Speaking during the commissioning ceremony, Headteacher Amos Mpamize Twine said the project commenced during the 2024/2025 Financial Year but experienced delays because the contractor lacked the capacity to execute the works within the expected timeframe.
He noted that although the main structures have been completed, several critical components remain unfinished.
"The main structures are complete, but several works are still pending. These include landscaping, planting trees and grass, drainage works, levelling the compound, installing inbuilt shelves and soft boards, and implementing environmental safeguards," Twine said.
Despite the delays, Twine said the new facilities have boosted public confidence in the school, contributing to a rise in student enrolment from 102 learners when construction began to 170 learners currently.
Kabale District Education Officer Moses Tumwijukye Bwengye said the classroom blocks were funded by the Ministry of Finance under the Transitional Development Fund at a total cost of Shs285 million.
He said the investment reflects government's continued commitment to improving learning infrastructure in public schools.